Power & Free. Installed for the Project Team.

Installation of a supplied power-and-free conveyor, with field layout coordination and overhead equipment integration in a finishing area.

Red power-and-free conveyor curves, overhead cable trays, and long panel load bars.
IMH responsibility
Installation · design and equipment supplied by others
Application
Overhead Conveyor
Customer reference
Confidential

The installation. Up close.

Follow the overhead route through the finishing area, from the supporting steel to the track curves and panel carriers.

The project starts
with the constraints.

Install a supplied power-and-free conveyor within a finishing-system project, coordinating overhead equipment and its supporting structure with the site layout.

  • Equipment design and components supplied by other parties
  • Supplied drawings and the physical site layout
  • Conveyor, support, and finishing-equipment interfaces

What IMH took on.

  • Installation of supplied conveyor equipment
  • Field layout coordination
  • Supplied drawing and installation interfaces

This project demonstrates IMH’s field installation work. Equipment design and supply are separate responsibilities.

Make the interfaces
work together.

01

Work from the supplied equipment scope.

The field record explicitly identifies IMH as the installer. Equipment design and components were supplied by others, making the installation responsibility distinct from system design ownership.

02

Coordinate the layout in the field.

The field records describe layout coordination and drawing updates based on the supplied information. That work connected the equipment package to the actual installation conditions.

03

Bring overhead equipment together.

The matched photographs show red conveyor track and carriers assembled on supporting steel, with panels hanging through the finishing area. Track curves, carrier connections, and the equipment below are visible together.

Proof in the work.

The field records document IMH’s installation work on the supplied conveyor system. The matched January and April 2025 photographs show the assembled overhead track, carrier connections, and suspended panels within the finishing area.

Define design, supply, installation, and startup responsibilities separately when preparing a partner installation scope.

A closer look at the work.

Two views from the installation floor. Select play to watch each 20-second clip, presented without audio.

The installation, in context.

A view across the finishing area showing the overhead conveyor, support steel, and surrounding installation work.

Under the overhead route.

A walkthrough beneath the red track curves, long load bars, and suspended panels.

Define the field interfaces before mobilization.

IMH installed equipment designed and supplied by others on this project. That scope makes drawing coordination, field layout, and responsibility for each equipment interface central to the installation plan.

Start the scope conversation.

Bring the supplied drawings, equipment list, site layout, and proposed responsibilities for supports, controls, utilities, and startup.

Plan work with an installation partner
Project references are anonymous to respect customer and partner relationships. Contact IMH to discuss the scope relevant to your application.

A better system
starts with a conversation.

A new line. A better lift. A demanding installation.
Bring us your goal. We’ll help define the next step.

Plan a project Or call (812) 363-1819